Project Overview
Current Phase: Discovery & Planning (Initiated)
Vendor
L.S.I
Objectives
Corporate website and internet booking engine development with Videcom integration
Alignment
Scope, governance, and high-level architecture successfully aligned
Dependencies
Progress pending critical inputs from Crown Airlines
Workstream Status
Content & Translations
Client-side responsibility
API & Integration
Videcom VARS XML
UAT & Governance
Stakeholder structure
Design Workshops
3 structured sessions
Project Milestones Timeline
Detailed Milestones
| # | Milestone | Owner | Dependency | Status |
|---|---|---|---|---|
| 1 | Kick-off Meeting | L.S.I / Crown | — | Completed |
| 2 | Sitemap Validation | Crown | — | Completed |
| 3 | Content Finalization | Crown | Client input | In Progress |
| 4 | Design Workshops | L.S.I | Content availability | Planned |
| 5 | API Test Credentials | Crown | Client input | Pending |
| 6 | API Integration & Testing | L.S.I | Test credentials | Pending |
Risks & Mitigation
| Risk | Impact | Mitigation |
|---|---|---|
|
Delay in content
delivery
|
Delays design and development phases | Early validation workshops and phased content intake |
|
Delay in API test
credentials
|
Blocks IBE integration testing | Parallel frontend development where possible |
Critical Pending Items
Content Delivery
Final content and translations from Crown Airlines
BLOCKING: Design & DevelopmentAPI Credentials
Test sales office / sine code for Videcom integration
BLOCKING: API TestingWorkshop Schedule
Confirmation of availability for 3 design workshops
REQUIRED: PlanningNext Week Action Items
| Action Item | Owner | Due Date | Priority | Status |
|---|---|---|---|---|
| Confirm content delivery timeline | Crown Airlines | Jan 28, 2026 | Critical | Awaiting |
| Provide test sales office credentials | Crown Airlines | Jan 29, 2026 | Critical | Awaiting |
| Confirm workshop availability (3 sessions) | Crown Airlines | Jan 30, 2026 | High | Awaiting |
| Prepare design workshop agendas | L.S.I | Jan 30, 2026 | Medium | In Progress |
| Finalize detailed project plan | L.S.I | Feb 2, 2026 | High | Pending Input |
| Circulate weekly status report | L.S.I | Feb 2, 2026 | Medium | Scheduled |
| Begin parallel frontend development | L.S.I | Feb 3, 2026 | Medium | Ready |
Crown Airlines Actions
Content & Translations
Confirm timeline for delivery
Test Credentials
Provide sales office / sine code
Workshop Availability
Confirm availability for design sessions
L.S.I Actions
Workshop Preparation
Prepare and circulate agendas
Project Planning
Finalize detailed project plan
Status Reporting
Maintain weekly project updates